Meta will donate $15 million this year to help El Paso Electric customers who need help paying their electricity bills, as well as provide another $38 million over the next 19 years for utility bill assistance and home energy efficiency improvements, the company said Tuesday.
The $53 million commitment comes as the social media giant continues building its sprawling $10 billion data center in Northeast El Paso.
The money will go to the Bright Hearts Fund, an existing partnership between El Paso Electric and the El Paso Community Foundation that helps customers who are behind on their electric bills and at risk of having their power disconnected.
Beginning next year, Meta will contribute $2 million annually to the fund through 2045 – a $38 million total donation. In addition to helping residents pay their bills, the money will also be available to pay for energy efficiency improvements in El Paso homes to reduce the amount of electricity a house consumes and lower its monthly bill.
Get help
Customers who are behind on their electric bills can seek assistance through the Bright Hearts Fund by contacting El Paso Electric’s customer care department.
- Phone: 800-351-1621
- Email: CustomerCare@epelectric.com
- Online chat: epelectric.com
“One thing we heard clearly is that energy costs are a challenge for El Pasoans,” Lauren Zimmerman, Meta’s community engagement manager in El Paso, said at a news conference in Downtown on Tuesday morning.
Meta didn’t specify how much of its annual $2 million contribution would go toward electric bill assistance versus weatherization projects.
Mayor Renard Johnson said his administration negotiated the commitment with Meta as city officials have sought to extract more benefits for El Pasoans from the company’s planned data center.
“This assistance won’t solve all of the affordability challenges families are facing, but it can help people who need a little extra help and a little extra support right now,” Johnson said.

Meta’s donation comes as city officials are also negotiating a community benefits agreement with Meta to fund various programs or projects around the city.
The City Council in June directed city staff to negotiate an agreement with Meta that would address environmental concerns, utility infrastructure and ratepayer protections, as well as prioritize hiring El Pasoans for the 300 permanent jobs Meta expects to create at the data center.
Some of the potential investments city officials have identified are funding for air-quality monitoring, solar-powered lights, job training programs and an expansion of the city’s tree-planting efforts, among others. The City Council is expected to discuss the community benefits agreement in the coming weeks.
READ MORE: Review El Paso Matters’ coverage of data centers
The tech giant Oracle is separately developing the Project Jupiter data center campus in nearby Doña Ana County, New Mexico, where it negotiated a community benefits agreement with the local government in exchange for the county granting a tax break. As part of that community benefits agreement, Oracle gave $50 million to the county to improve water infrastructure in the area of Sunland Park and Santa Teresa.
Meta’s El Paso power plant
In El Paso, hundreds of residents have voiced concerns to city officials about Meta’s data center, which the company expects to employ 300 people when it’s operating and 4,000 construction jobs during development.
The City Council in June voted 5-3 against a proposal to pursue termination of the city’s tax incentive agreement with Meta following hours of public comment. The following month, council adopted a policy framework aimed at more tightly regulating future data center developments.
Zimmerman said the company plans to cover all the costs of supplying electricity and water to its data center to prevent those costs from being passed on to El Paso households and businesses. But there are complexities.
El Paso Electric is seeking approval from the Public Utility Commission of Texas to build a large power plant – called the McCloud plant – specifically to power Meta’s data center starting next year.
The project is expected to cost about $552 million, including the cost of eventually connecting it to the regional power grid. Under El Paso Electric’s proposal, the plant would connect solely to Meta’s data center for up to five years.
After that five years, El Paso Electric wants to incorporate the McCloud plant into its fleet of power plants serving all of its customers, meaning the cost of the plant would be added to all customers’ bills rather than only charged to Meta.
Two administrative law judges overseeing El Paso Electric’s application to build the plant in September recommended that the state’s utility commissioners approve the plant’s construction only if El Paso Electric ensures Meta pays the full cost of McCloud for the life of the facility.
The Public Utility Commission is expected to issue a final decision on the power plant in December – a key hurdle still remaining before Meta’s data center can start operating.
Construction of the McCloud facility has already started, however. Executives of ERock – the company formerly called Enchanted Rock that is building McCloud – said on the company’s quarterly earnings call earlier this month that construction was underway.
“Our El Paso Electric project moved from mobilization into active construction,” John Carrington, ERock’s chief executive, told Wall Street analysts Nov. 12. “Most of our civil work is complete and gen sets began arriving on site earlier this month. We expect to complete installation by mid-2027.”
The McCloud plant will supply about 225 megawatts of electricity to Meta’s data center, which will eventually require 1,000 megawatts when it’s fully built.
El Paso Electric is also seeking state approval to build a high-voltage transmission line connecting a planned substation in far East El Paso to another substation near the Meta data center so the utility can ferry electricity from regional solar farms and power plants to the data center campus.
Oracle proposes bill credits in Southern New Mexico
Meanwhile, Oracle moved first to offer utility bill credits to El Paso Electric customers in New Mexico as the company has sought to build regulatory and political support for Project Jupiter.
Oracle announced a proposal last month to provide up to $55 million annually for three years in electric bill credits for El Paso Electric’s residential and small-business customers in New Mexico.
But alongside the offer of customer bill credits, Oracle announced it was pursuing a deal with El Paso Electric to connect Project Jupiter to the regional power grid, which would provide electricity during portions of the data center’s construction and serve as a backup power source once the facility is operating.
Doña Ana County commissioners immediately balked at the proposal during an Oct. 13 meeting with Oracle representatives.

Commissioners approved billions of dollars in tax incentives for Project Jupiter last year with the understanding that the data center would generate its own electricity in an isolated microgrid. The project’s developers are seeking to build a 2,450-megawatt natural gas-powered fuel cell facility to power the data center. The county commissioners questioned whether connecting Project Jupiter to El Paso Electric’s grid would increase bills for the utility’s customers.
Two weeks later, Doña Ana County commissioners unanimously voted to notify Project Jupiter’s developers of a potential breach of the agreements over the proposed power supply arrangement — essentially rejecting Oracle’s customer bill credit idea.
Meta donations
Meta’s announcement Tuesday follows a series of contributions the company has made to nonprofit organizations and other institutions in El Paso this year.
The company provided $2.5 million in matching funds for El Paso Giving Day in October, helping the annual fundraiser generate a record of roughly $7.3 million for regional nonprofits.
Meta also announced a $500,000 grant in March to support workforce development and career and technical education in El Paso schools, and donated $25,000 this year to El Paso Water’s AguaCares program for bill assistance.
Zimmerman said Tuesday the company has also donated to several community events, including the Amigo Airsho, the Old El Paso Sun Bowl and WinterFest. And she said Meta would “soon” sponsor athletics at the University of Texas at El Paso but didn’t offer more details.
Johnson said Tuesday he expects his administration to continue pursuing commitments from Meta to invest in the community.
“If they’re going to be a part of this community, we’re going to hold them accountable. We’re going to ask them to do more for El Paso,” Johnson said. “This is just one step in the right direction.”
The post Meta pledges $53 million to help El Paso Electric customers pay bills, lower energy costs appeared first on El Paso Matters.